Project Portfolio

CLIENT WORK COST OF WORK COMPLETION OF WORK LOCATION
JAKSON LABORATORIES 4.5 CRORE 6 MONTHS AMRITSAR
HYUNDAI SHOWROOM 3.5 CRORE 8 MONTHS KULLU MANALI (HILLY AREA)
SANGAM AUTOMOBILES 2.10 CRORE 5 MONTHS AMRITSAR
MIDTOWN HOTEL 3 CRORE 8 MONTHS AMRITSAR
BHINDER FARMS 1.5 CRORE 8 MONTHS TARN TARAN ROAD
NATRAJ WOOLTEX 30 LAKHS 1 MONTH AMRITSAR
RANA SUGAR MILLS 5 CRORE 8 MONTHS BATALA
JCT MILLS 10 CRORE 13 MONTHS HOSHIARPUR
TRIDENT FACTORY 4.5 CRORE 5 MONTHS BARNALA
ROHAN & RAJDEEP BUS STAND 20 CRORE 7 MONTHS AMRITSAR
PRIM ROSES PUBLIC SCHOOL 3.5 CRORE 7 MONTHS AMRITSAR
MILLENNIUM SCHOOL 1 CRORE 6 MONTHS AMRITSAR
LT FOODS LTD (DAWAT RICE) 4.5 CRORE 7 MONTHS MANDI AHMEDGARH
VR AMBARSAR 20 LAKHS 4 MONTHS AMRITSAR
AVENUE SUPERMARTS LIMITED (D-MART)

Steel, RMC and Cement were supplied by the client (F.O.C.). The scope of work included the Main Building, Waterproofing, Compound Wall, Grass Paver, and other civil works.
7.5 CRORE 10 MONTHS KHASA, AMRITSAR
JAKSON LABORATARYS


Cost of Work: 4.5 CRORE
Completion of Work: 6 Months
Location: Amritsar

HYUNDAI SHOWROOM


Cost of Work: 3.5 CRORE
Completion of Work: 8 Months
Location: KULLU MANALI (HILLY AREA)

SANGAM AUTO MOBILES


Cost of Work: 2.10 CRORE
Completion of Work: 5 Months
Location: Amritsar

MIDTOWN HOTEL


Cost of Work: 3 CRORE
Completion of Work: 8 Months
Location: Amritsar

BHINDER FARMS


Cost of Work: 1.5 CRORE
Completion of Work: 8 Months
Location: Tarn Taran Road

NATRAJ WOOLTAX


Cost of Work: 30 LAKHS
Completion of Work: 1 Months
Location: Amritsar

RANA SUGAR MILLS


Cost of Work: 5 CRORE
Completion of Work: 8 Months
Location: Batala

JCT MILLS


Cost of Work: 10 CRORE
Completion of Work: 13 Months
Location: Hoshiarpur

TRIDENT FACTORY


Cost of Work: 4.5 CRORE
Completion of Work: 5 Months
Location: Barnala

ROHAN & RAJDEEP BUS STAND


Cost of Work: 20 CRORE
Completion of Work: 7 Months
Location: Amritsar

PRIM ROSES PUBLIC SCHOOL


Cost of Work: 3.5 CRORE
Completion of Work: 7 Months
Location: Amritsar

LT FOODS LTD (DAWAT RICE)


Cost of Work: 4.5 CRORE
Completion of Work: 7 Months
Location: Mandi Ahmedgarh

MILLINIUM SCHOOL


Cost of Work: 1 CRORE
Completion of Work: 6 Months
Location: Amritsar

VR AMBARSAR


Cost of Work: 20 LAKHS
Completion of Work: 4 Months
Location: Amritsar

AVENUE SUPERMARTS LIMITED ( D-MART)

Steel, RMC, and Cement was client supply F.O.C and work done in this project are Main Building, Water Proofing, Compound Wall, Grass Paver and etc..."

Cost of Work: 7.5 CR
Completion of Work: 10 Months
Location: Khasa - Amritsar